CONSTRUCTION OF OUR NEW SEAT

01 June 2013

In June 2013, we have submitted an application for co-financing from resources of EU’s Innovative Economy Operational Programme for the years 2007–2013, Measure 4.4 “New investments of high innovative potential”.

While our application for funding was screened according to applicable procedures, in August we realised the tendering process as a result of which we were able to select a most favourable offer for construction work.

After signing a contract with the construction company, on the 1st of October 2013 we have handed the construction site to the Contractor and the construction work started at full steam. The new building will comprise the office space, storage areas, and production shops equipped with up-to-date machines which allow us to extend our offer in scope of filter elements and oil filtration devices. The new building will accommodate also a modern laboratory which will allow us to broaden the range of services rendered by us in the area of laboratory analyses of oils.

On 9 October 2013 we have received the decision of the Polish Agency for Enterprise Development qualifying of our application for funding and in November we have signed the relevant agreement.

Thanks to such fortunate turn of events, the new building was into operation in September 2014.